Rebuilding After the Palisades Fire: A Step-by-Step Look at the Recovery and Reconstruction Process

Phase 1: Emergency Response & Environmental Site Clearance

EPA Cleanup After a Wildfire

The first step after a fire in Los Angeles County is environmental clearance. The Environmental Protection Agency (EPA) is typically the first agency on-site, ensuring all hazardous materials—like asbestos, lead, and household chemicals—are safely removed.

At 1041 Iliff, the EPA conducted a full Phase 1 debris removal, which included:

    • Hazardous material identification and removal

    • Air quality testing

    • Safety clearance to prevent environmental contamination

Army Corps of Engineers & Phase 2 Debris Removal

Once EPA finished their part, the U.S. Army Corps of Engineers stepped in for Phase 2 cleanup, which involved:

    • Deep debris removal down to the soil

    • Removal of damaged concrete foundations and footings

    • Initial soil testing and compaction reports

This phase is mandatory before any rebuilding can begin in a wildfire-affected zone in Los Angeles.

Phase 2: Site Prep and Clearing for Rebuild

After environmental clearance, we began preparing the site for reconstruction:

    • Cleared remaining debris and tree stumps

    • Removed fire-damaged utilities and infrastructure

    • Completed grading, compaction, and topographic surveys

    • Verified lot lines, setbacks, and slope conditions for compliance

Proper grading and soil compaction is critical to passing LADBS (Los Angeles Department of Building and Safety) inspections for new construction.

Phase 3: Architectural Planning and Permitting

At this stage, our goal was to rebuild the home identical to its previous layout, incorporating a few key upgrades:

    • A new tile roof (approved upgrade)

    • Window upgrades from vinyl to aluminum grid doors by Lincoln

    • A 10% square footage increase (~380 sq. ft.) while maintaining the original architectural footprint

We collaborated with our architectural and structural engineering teams to:

    • Replicate the home’s last renovation (originally designed by Mandy Chang)

    • Update structural calculations for new roofing and layout modifications

    • Prepare full plan sets for LADBS submittal

Permitting Process in Los Angeles

Permitting in LA is a multi-step process that includes:

    • Architectural review

    • Structural plan check

    • Soil & grading approval

    • Energy compliance (Title 24)

    • Green building compliance

We also worked with our expediters to streamline reviews and minimize delays.

What’s Next: Rebuilding the Palisades Home

With permits nearly complete and upgrades approved, we’re scheduled to begin construction this summer. Our team at LA Design Build is committed to delivering a modern, high-performance home—one that honors the original design while enhancing safety, energy efficiency, and long-term value.

Stay tuned for the next phase: Framing and Foundation Work—where we’ll go behind the scenes of building the new structure from the ground up.

Recent work

A Snapshot of Our Projects.

View All Projects
Hover a panel to open it. Click to step inside.
All images are photographs of LA Design Build projects. Encino photography: Madeline Tolle.
Press

As Seen In.

Architectural Digest MyDomaine Luxe Interiors + Design Dwell House Beautiful Rue Magazine
Questions

Building with LA Design Build.

Do you rebuild homes lost in the Palisades fire?

Yes. We’re currently rebuilding a home lost in the January 2025 Palisades fire — 1041 Iliff Street — as a Spanish Modern of about 5,200 square feet. It’s already cleared plan check and passed rough framing, so you can see the process in real time.

Can I bring my own architect or designer?

Yes. We work with many architects and designers and would welcome yours. We respect the design and can’t wait to bring your vision to life.

What does a custom home cost?

Every project is different, so we walk through material selections together for a transparent budget with clear allowances. Projects typically start at $650 per square foot and up, and we lock that number before breaking ground.

Where do you build?

Pacific Palisades, Brentwood, Bel Air, Beverly Hills and the Hollywood Hills.

What’s the typical timeline for a custom build?

If you have your plans ready and materials are selected, our typical timeline is 12 to 14 months.