The first step after a fire in Los Angeles County is environmental clearance. The Environmental Protection Agency (EPA) is typically the first agency on-site, ensuring all hazardous materials—like asbestos, lead, and household chemicals—are safely removed.
At 1041 Iliff, the EPA conducted a full Phase 1 debris removal, which included:
Once EPA finished their part, the U.S. Army Corps of Engineers stepped in for Phase 2 cleanup, which involved:
This phase is mandatory before any rebuilding can begin in a wildfire-affected zone in Los Angeles.
After environmental clearance, we began preparing the site for reconstruction:
Proper grading and soil compaction is critical to passing LADBS (Los Angeles Department of Building and Safety) inspections for new construction.
At this stage, our goal was to rebuild the home identical to its previous layout, incorporating a few key upgrades:
We collaborated with our architectural and structural engineering teams to:
Permitting in LA is a multi-step process that includes:
We also worked with our expediters to streamline reviews and minimize delays.
With permits nearly complete and upgrades approved, we’re scheduled to begin construction this summer. Our team at LA Design Build is committed to delivering a modern, high-performance home—one that honors the original design while enhancing safety, energy efficiency, and long-term value.
Stay tuned for the next phase: Framing and Foundation Work—where we’ll go behind the scenes of building the new structure from the ground up.
01Transitional Farmhouse01 / 13Transitional FarmhouseEncino View project →
02Commonwealth Residence02 / 13Commonwealth ResidenceOur build, featured in Architectural Digest View project →
03The Color-Drenched Modern Residence03 / 13The Color-Drenched Modern ResidenceCulver City View project →
04Brentwood04 / 13BrentwoodArchitectural Edition View project →
05Marina Crest05 / 13Marina CrestOcean View Penthouse View project →
06The Delaware Residence06 / 13The Delaware ResidenceBurbank View project →
07Azzurra Penthouse07 / 13Azzurra PenthouseView project →
08Los Feliz Elegance08 / 13Los Feliz EleganceView project →
091011 Skyline Lux09 / 131011 Skyline LuxView project →
10Galleon Residence10 / 13Galleon ResidenceModern Farmhouse View project →
11Modern Penthouse 82911 / 13Modern Penthouse 829View project →
12Maison Élégante12 / 13Maison ÉléganteGrand Canal, Venice View project →
13Pied-à-Terre13 / 13Pied-à-Terre1517 View project →
Yes. We’re currently rebuilding a home lost in the January 2025 Palisades fire — 1041 Iliff Street — as a Spanish Modern of about 5,200 square feet. It’s already cleared plan check and passed rough framing, so you can see the process in real time.
Yes. We work with many architects and designers and would welcome yours. We respect the design and can’t wait to bring your vision to life.
Every project is different, so we walk through material selections together for a transparent budget with clear allowances. Projects typically start at $650 per square foot and up, and we lock that number before breaking ground.
Pacific Palisades, Brentwood, Bel Air, Beverly Hills and the Hollywood Hills.
If you have your plans ready and materials are selected, our typical timeline is 12 to 14 months.